ReportWire

Tag: Bodies of water

  • Country club’s plan to cut down trees paused by Planning Board

    [ad_1]

    NORTH ANDOVER — The Planning Board wants a local country club to do its due diligence before allowing it to cut down more than 30 trees along the lake that serves as the town’s water supply.

    The Planning Board denied an application from the North Andover Country Club for an emergency watershed special permit at its meeting Tuesday.

    This page requires Javascript.

    Javascript is required for you to be able to read premium content. Please enable it in your browser settings.

    kAmq@J5 w@=<[ E96 4@F?ECJ 4=F3’D 86?6C2= >2?286C[ AC@A@D65 C6>@G:?8 b` FA=2?5 EC66D @? E96 AC@A6CEJ 2E d__ vC62E !@?5 #@25 E92E 2C6 H:E9:? E96 9:89H2E6C 6=6G2E:@? @7 {2<6 r@49:496H:4< 2?5 E96 E@AA:?8 @7 =2C86 D9CF3D]k^Am

    kAm%C66D 2?5 D9CF3D AC@A@D65 E@ 36 C6>@G65 2C6 @? E96 hE9 72:CH2J 2=@?8 E96 =2<6 36EH66? E96 4=F3’D A=2J8C@F?5 2?5 E6??:D 4@FCED] $9CF3D H@F=5 36 E@AA65 2C@F?5 E96 `DE 2?5 hE9 72:CH2JD]k^Am

    kAm%96 6>6C86?4J C6BF6DE 2AA=:42E:@?[ AC6A2C65 3J |6CC:>24< t?8:?66C:?8 $6CG:46D[ D2:5 E96 EC66D 4@G6C65 3J E96 AC@A@D2= H6C6 4@>AC@>:D65 27E6C 36:?8 DF3>6C865 😕 9:89 H2E6CD]k^Am

    kAm%96 EC66 C6>@G2=[ w@=< E@=5 E96 3@2C5[ H@F=5 2=D@ 96=A E96 4@F?ECJ 4=F3 36EE6C AC6A2C6 7@C 7FEFC6 7=@@5 6G6?ED 2?5 2G@:5 D:EF2E:@?D H96C6 5625 EC66D 42FD6 >@C6 92C>]k^Am

    kAm%96 EC66D AC@A@D65 E@ 36 4FE 5@H? 2C6 ?@E ?2E:G6 E@ E96 H6E=2?5 2C62 2?5 H@F=5 ?@E DFCG:G6 =@?8 E6C> :7 DF3>6C865 F?56C H2E6C 282:? 5FC:?8 7=@@5D =:<6 E96 @?6 E92E 9:E E96 |6CC:>24< ‘2==6J 😕 a_ab[ w@=< D2:5]k^Am

    kAm“pD 2 4=F3[ H6 92G6 ?@ :562 :7 H6 2C6 6G6C 8@:?8 E@ 86E 7=@@5D 282:? =:<6 H6 925 E92E J62C[ 3FE H6 4@F=5 92G6 >F=E:A=6 @?6D[” 96 D2:5]k^Am

    kAm%96 6>6C86?4J A6C>:E H2D D@F89E 3642FD6 @7 E96 4=F3’D D9@CE H:?5@H @7 y2?F2CJ E@ u63CF2CJ 7@C E96 8C@F?5 E@ 36 7C@K6? 2?5 2==@H 962GJ ECF4286 E@ :E]k^Am

    kAms:C64E@C @7 !=2??:?8 y62? t?C:89E D2:5 E96C6 😀 2? 6>6C86?4J A6C>:E AC@G:D:@? 😕 E96 3J=2H] x? 96C E:>6[ t?C:89E DE2E65 E92E D96 92D ?6G6C D66? @?6 D@F89E @C 2AAC@G65] $96 D2:5 D96 42FE:@?65 E96 2AA=:42?E E96 3@2C5 >2J H2?E E@ 4@?D:56C 6:E96C 2 DE@C>H2E6C @C 2C3@C:DE C6G:6H]k^Am

    kAm$96 25565 E92E E96 r@?D6CG2E:@? r@>>:DD:@? H@F=5 =:<6=J H2?E E@ D66< 2 C6G:6H 3J 2? 2C3@C:DE 2D E@ E96 EC66D’ 962=E9[ 2?J 67764E @? E96 D9@C6=:?6 :7 E96J 2C6 C6>@G65[ 2?5 2?J :>A24E E@ E96 =2<6]k^Am

    kAmr92:C t:E2? v@=536C8 D2:5 E96 AC@A@D2= 5@6D ?@E 42== 7@C 2? 6>6C86?4J AC@G:D:@? 2?5 ?665D E@ 8@ E9C@F89 E96 AC@A6C AC@46DD @7 2AAC@G2= — 2DD6DD>6?ED[ A66C C6G:6HD 2?5 AF3=:4 962C:?8D — 3642FD6 @7 9@H 4=@D6 E96 EC66D 2C6 E@ 2? :>A@CE2?E 2DD6E]k^Am

    kAmq@2C5 >6>36C !6E6C q@J?E@? D2:5 96 H2D 96D:E2?E E@ 4FE EC66D 😕 2 H2E6CD965 4=@D6 E@ E96 =2<6[ DEC6DD:?8 9@H E96 =2<6 😀 E96 D@=6 D@FC46 @C 5C:?<:?8 H2E6C 😕 E@H? H9:49 ?665D E@ 36 AC@E64E65] ‘686E2E:@? 2=@?8 E96 D9@C6=:?6 A=2JD 2 A2CE 😕 AC@E64E:?8 E96 H2E6C[ 7:=E6C:?8 DE@C>H2E6C 2?5 96=A:?8 AC6G6?E 6C@D:@? 367@C6 :E 86ED E@ E96 =2<6]k^Am

    kAmq@J?E@? 42==65 E96 4@F?ECJ 4=F3 2? “:?DE:EFE:@?2= =2?5@H?6C E@ AC@E64E 2? 2DD6E E92E 27764ED 6G6CJ D:?8=6 A6CD@? 😕 E@H?]”k^Am

    kAm“*@F 2C6 E96 ?6:893@C @7 6G6CJ C6D:56?E @7 E@H?[” q@J?E@? D2:5]k^Am

    kAmv@=536C8 2=D@ D2:5 E96 3@2C5 92D 8@?6 E9C@F89 =6?8E9D E@ E6== A6@A=6 ?@E E@ 4FE 5@H? EC66D 2?5 AF?:D965 E96> H96? E96J 92G6 5@?6 :E H:E9@FE 8@:?8 E9C@F89 E96 3@2C5’D C6G:6H]k^Am

    kAm%96 3@2C5 56E6C>:?65 E96 6>6C86?4J A6C>:E 5:5 ?@E >66E 4C:E6C:2 7@C :E E@ 36 :DDF65[ 3FE EC66 C6>@G2= 😀 D@>6E9:?8 E92E 42? 36 C6G:6H65 H96? 8@:?8 E9C@F89 E96 2AAC@AC:2E6 A6C>:EE:?8 AC@46DD]k^Am

    [ad_2]

    By Angelina Berube | aberube@eagletribune.com

    Source link

  • Haverhill to borrow $12.4M to reduce CS0s, upgrade water lines

    Haverhill to borrow $12.4M to reduce CS0s, upgrade water lines

    [ad_1]

    HAVERHILL — The city will borrow $12.4 million for a project aimed at reducing the amount of combined sewer overflows reaching the Merrimack River.

    The City Council this week unanimously approved borrowing $12.4 million for a project intended to reduce CSOs pouring into the Little River and into the Merrimack River while also improving the water distribution system in the Locke Street area.

    In his request for the funding, DPW Director Robert Ward told the council the amount of the loan order increased by about $2 million since the original request passed about a year ago.

    He said the project was deferred a year due to permitting issues hit by cost increases.

    He said a number of things, including the need for additional quantities of items such as 18-inch diameter pipes, the creation of additional stormwater outfalls not in the original cost estimates, the need to rehabilitate some stormwater drain pipes, additional roadway restoration costs and other items.

    The council was provided with documents explaining the project, which will play out in three phases over the next 10 years.

    In his letter to the council, Ward noted that in 2016 the city entered into a consent decree with the federal Environmental Protection Agency (EPA) and the Massachusetts Department of Environmental Protection (DEP) requiring the city to reduce CSOs.

    Ward said that before the 1960s, sewage and stormwater were commonly collected in the same pipe. These combined sewers were designed and built to overflow into nearby waterways to prevent excessive flooding during rain storms from backing up into basements, streets, parking lots and other areas.

    Ward said the Locke Street area is the city’s biggest contributor to CSO overflows into the Merrimack River.

    This Locke Street Phase 1 combined sewer overflow (CSO) separation and water system improvements project will involve separating the combined sewer system in that area into separate wastewater and stormwater systems, thereby reducing excessive stormwater entering the sewer system during rain events.

    Ward noted that Phase 1 separates about 3,500 feet of combined sewers in the Locke Street area by installing new stormwater pipes, disconnecting catch basins from them, and connecting them to the separate stormwater lines. The project also involves upsizing existing storm drains, installing new outfalls to increase capacity of the existing storm drain system, and rehabilitating existing sewers and manholes.

    In conjunction with the sewer and drain work, old, undersized water mains in the Phase 1 area will be replaced and upsized. Ward said it makes sense to upgrade water lines in that area rather than return at a future date and having to dig up the streets again.

    The average household’s sewer rate impact from this project will be less than $21 annually, Ward stated in his letter. The water rate impact will add about $8 to the annual bill for an average size household, he said.

    The loan order funds Phase 1 of three phases over the next 10 years or so. Phases 2 and 3 will be in other areas, including Primrose, Main Street and Lawrence Street, which also discharge into Little River and to the CSO outlet behind the downtown bus station.

    “We’re paying for the sins of the past,” Ward said.

    [ad_2]

    By Mike LaBella | mlabella@eagletribune.com

    Source link

  • Missing Dog Returns Home After 150-Mile Trek Across Bering Sea Ice

    Missing Dog Returns Home After 150-Mile Trek Across Bering Sea Ice

    [ad_1]

    A lost 1-year-old Australian shepherd survived a 150-mile trek across frozen Bering Sea ice before being safely returned to his home in Alaska. What do you think?

    “I’m glad he was reunited with the people he was desperately trying to escape.”

    Eli Alston, Gunk Inspector

    “This wouldn’t have happened if the owners had adhered to Bering Strait leash laws.”

    Becky Russo, Date Strategist

    “It’s gonna be wild when they put this dog down.”

    Lee Courtwright, Systems Analyst

    [ad_2]

    Source link