Bolts that helped secure a panel to the frame of a Boeing 737 Max 9 were missing before the panel blew off the Alaska Airlines plane last month, according to accident investigators.

The National Transportation Safety Board issued a preliminary report on the Jan. 5 incident Tuesday.

The report included a photo from Boeing, which worked on the panel, which is called a door plug. In the photo, three of the four bolts that prevent the panel from moving upward are missing. The location of the fourth bolt is obscured.

The investigators said that the lack of certain damage around the panel indicates that all four bolts were missing before the plane took off from Portland, Oregon.

Pilots were forced to make a harrowing emergency landing with a hole in the side of the plane.

Without the bolts, nothing prevented the panel from sliding upward and detaching from “stop pads” that secured it to the airframe.

The preliminary report said the door plug, installed by supplier Spirit AeroSystems, arrived at Boeing’s factory near Seattle with five damaged rivets around the plug. A Boeing crew replaced the damaged rivets, which required them to remove the four bolts to open the plug.

Safety experts have said the accident could have been catastrophic if the Alaska jet had reached cruising altitude. The decompression in the cabin after the blowout would have been far stronger, and passengers and flight attendants might have been walking around instead of being belted into their seats.

Although the preliminary report noted Spirit’s role in the incident, Boeing CEO David Calhoun said last week that the company caused the problem.

“I want everybody — everybody on every airplane — to know that Boeing owns it. We own our supply chain. We own Spirit. We own the results of our work,” Calhoun said on CNBC.

The incident has added to questions about manufacturing quality at Boeing that started with the deadly crashes of two Max 8 jets in 2018 and 2019, killing 346 people.

The Federal Aviation Administration is investigating whether Boeing and its suppliers followed proper safety procedures in manufacturing parts for the Max. The FAA has barred Boeing from speeding up production of 737s until the agency is satisfied about quality issues.

FAA Administrator Michael Whitaker said Tuesday that his agency is about halfway through a six-week audit of manufacturing processes at Boeing and its key supplier on the Max, Spirit AeroSystems. He said the agency is confronted with two questions — what’s wrong with the Max 9, and “what’s going on with the production at Boeing?”


Source link

You May Also Like

Rutgers University educators set to go on strike in what would be massive, historic walkout

9,000 Rutgers University faculty members set to strike Monday 9,000 Rutgers University…

How to Travel Europe on a Budget

IC Production / Shutterstock.com Editor's Note: This story originally appeared on Live…

Purina recalls dog food due to elevated levels of vitamin D

Nestlé Purina PetCare has expanded its recall of a prescription dog food…

How Often Does Social Security Recalculate Your Retirement Benefits? – NerdWallet

The Social Security Administration recalculates your benefits annually, which means the amount…